By Justine Irish D. Tabile, Senior Reporter

INFRASTRUCTURE SPENDING grew by 14% year on year in September, its first annual increase in over a year, Department of Budget and Management (DBM) data showed.

In its latest National Government disbursement report, the DBM said spending on infrastructure and other capital outlays went up by P11 billion to P89.7 billion in September from P78.7 billion in the same month in 2025.

This was the first year-on-year rise in infrastructure spending since June 2025.

Month on month, infrastructure spending, excluding infrastructure subsidies and equity to government-owned and -controlled corporations as well as infrastructure transfers to local government units, also increased by 27.3% from P70.5 billion in August.

“The increase reflected higher payments for road infrastructure requirements processed under applicable project validation, documentation, and financial control procedures,” the DBM said.

Infrastructure spending has recorded annual declines since July 2025, when President Ferdinand R. Marcos, Jr. ordered an audit and performance review of flood control projects amid allegations of corruption and substandard quality. The move led to heightened scrutiny of public works projects and tighter verification requirements for government disbursements.

Francisco Cid L. Terosa, an associate professor and former dean of the University of Asia and the Pacific School of Economics, said the September increase signals an improvement in the government’s infrastructure spending momentum, although this could also be partly attributed to a low base.

“I would call it a catch-up drive by the government after months of contracted spending. A low year-ago comparison base can also be cited as one reason for the growth in infra and other capital outlays,” he said.

In the third quarter, infrastructure spending slid by 2.7% to P249.9 billion from P256.9 billion a year ago.

It was also 0.6% lower than the programmed infrastructure and other capital outlays of P251.3 billion for the third quarter.

Meanwhile, infrastructure spending in the first nine months declined by 30.3% to P611.7 billion from P877.1 billion in the same period last year.

“Procurement compliance, oversight of ongoing projects, payment claims verification, and contractor documentation were strengthened to ensure that payments correspond to properly validated and documented works,” the DBM said.

“Nevertheless, the ongoing implementation of non-road infrastructure projects across other key sectors provided significant support to the overall infrastructure disbursements,” it added.

The non-road infrastructure projects include defense modernization projects under the Department of National Defense, school-building projects of the Department of Education, and flagship railway projects of the Department of Transportation.

Despite the nine-month decline, infrastructure and other capital outlays were 1.4% higher than the programmed P603.1 billion for the January-to-September period.

The DBM attributed the higher-than-programmed spending to additional releases to the Department of Public Works and Highways (DPWH) for mobilization costs, right-of-way claims, and the settlement of accounts payable under the 2026 and 2025 General Appropriations Acts.

OUTLOOK
The DBM said public construction fell by 15.1% in the third quarter, easing from the 33.4% decline in the preceding quarter.

“The implementation of infrastructure projects in the third quarter was constrained by weather disruptions, while efforts to strengthen infrastructure governance and ensure public spending efficiency were also undertaken through stricter project validation and payment claims verification procedures,” the DBM said.

For the fourth quarter, the DBM expects capital outlays of the DPWH, defense modernization projects, and disaster rehabilitation and reconstruction programs, among others, to sustain government spending growth.

Mr. Terosa said the low base brought about by corruption audits in 2025 could also prop up infrastructure spending growth in the fourth quarter.

“The end of the habagat season will enable construction works to accelerate and contractor billings to be higher in Q4 2026,” he said.

However, Mr. Terosa said the government is unlikely to meet its full-year infrastructure spending program amid continued stringent audit and procurement requirements.

“A full catch-up with the annual spending program is unlikely. The year-to-date deficit may not be erased in just two to three months,” he said.

“Audit and procurement standards have remained strict, stalling the pace of infrastructure and capital outlays,” he added.

Under the 2027 Budget of Expenditures and Sources of Financing, the NG’s full-year disbursement program for infrastructure and other capital outlays is set at P931.54 billion for 2026.

As of end-September, the government still needed to spend about P319.84 billion in the fourth quarter to meet its full-year program.

Meanwhile, Senator Joseph Victor G. Ejercito, who chairs the Senate Committee on Finance, said during Monday’s interpellations on the proposed 2027 national budget that the economy could have grown by 4.1% in the first three quarters had public infrastructure projects not been delayed.

“Delays in public infra projects contributed to the slowdown in economic growth. Public construction delays reduced gross domestic product growth by 0.5 percentage point (ppt) in the third quarter, and by 1.6 ppts in the first three quarters,” he said.

“According to (Economy) Secretary Arsenio M. Balisacan, growth should be about 4.1%… in the first three quarters instead of 2.5%,” he added.

The Philippine economy grew by 2.5% in the first three quarters, amid weak household consumption growth and a 4.4% contraction in gross capital formation. This was below the government’s 3.5%-4.5% growth target for 2026.